Yvon and Noella Cormier of Andover donated $1.5 million to the Town of Andover for a youth center in West Andover.  Under the agreement with the Andover Youth Foundation, the town will provide 6 acres in West Andover. The center would be called the Cormier Family Youth Center. Yvon owns the Cormier Construction Company.
Yvon and Noella Cormier of Andover donated $1.5 million to the Town of Andover for a youth center in West Andover.  Under the agreement with the Andover Youth Foundation, the town will provide 6 acres in West Andover. The center would be called the Cormier Family Youth Center. Yvon owns the Cormier Construction Company.


Funding and other issues delay a June 2006 start date for construction of a Youth Center.  
Funding and other issues, such as playing field availability and the proximity of a landfill, plagued the project for the West Andover site. In December of 2005 $1 million dollar in infrastructure costs were added to the price tag delaying a June 2006 start date for construction of a Youth Center.  


In 2006, a location downtown was discussed, but the article asking the Town for $900,000 was withdrawn from the Town Warrant.  Selectman Brian Major suggested a Special Town Meeting in the fall to deal with the youth center.
In 2006, a location downtown was discussed, but the article asking the Town for $900,000 was withdrawn from the Town Warrant.  Selectman Brian Major suggested a Special Town Meeting in the fall to deal with the youth center.


The 2007 Town Meeting voted to use land behind Doherty Middle School. The suggestion was made at that time to build space that would be shared as a Youth Center and a Senior Center. Funding continued to be an issue.  A private foundation - the Andover Youth Foundation was established to raise money and coordinate the process of building a youth center. Peg Campbell was promoted to the Foundation's president in June of 2007.  
The 2007 Town Meeting voted to use land behind Doherty Middle School. The suggestion was made at that time to build space that would be shared as a Youth Center and a Senior Center. Funding continued to be an issue.  A private foundation - the Andover Youth Foundation was established to raise money and coordinate the process of building a youth center. A public project is required to pay state-set prevailing wages. Since a private organization is not the cost of the project is reduced substantially. Peg Campbell was promoted to the Foundation's president in June of 2007.  


The Special Town Meeting in the Spring of 2013 approved using half of the $1.4 million Wood Trust (a fund established for the benefit of senior citizens) on the new Cormier Family Youth Center. The funding of the Cormier Family Youth Center came from a combination of town money and fundraising.  
The Special Town Meeting in the Spring of 2013 approved using half of the $1.4 million Wood Trust (a fund established for the benefit of senior citizens) on the new Cormier Family Youth Center. The funding of the Cormier Family Youth Center came from a combination of town money and fundraising.  
Line 25: Line 25:
*"Youth Center $75,000 Richer," ''Andover Townsman'', November 5, 2001.
*"Youth Center $75,000 Richer," ''Andover Townsman'', November 5, 2001.
*"$120K raised at Telethon for Youth Center," ''Andover Townsman'', February 12, 2004.
*"$120K raised at Telethon for Youth Center," ''Andover Townsman'', February 12, 2004.
*"Youth Center Price Tag Grows to $4.2 Million", ''Eagle Tribune'', December 22, 2005.
*"New Center Further off Schedule," ''Boston Globe'', January 22, 2006.
*"New Center Further off Schedule," ''Boston Globe'', January 22, 2006.
*"Fall Meeting Discussed for Youth Center Vote," ''Andover Townsman'', April 6, 2006.
*"Fall Meeting Discussed for Youth Center Vote," ''Andover Townsman'', April 6, 2006.
*"New Youth Center Leader Wants Project Finished in 2 Years", Andover Townsman, June 14, 2007, page 1 and 2.  
*"New Youth Center Leader Wants Project Finished in 2 Years", ''Andover Townsman'', June 14, 2007, page 1 and 2.
*"Foundation: Pact Could Save $1M-plus", ''Andover Townsman'', June 21, 2007
*"State Ruling Could Save $1M on Youth Center", Eagle Tribune, July 18, 2007 page 1 and 3.  
*"Youth Center May Cost Extra $2M", ''Eagle Tribune'', September 28, 2007 page and 8.
*"Youth Center May Cost Extra $2M", ''Eagle Tribune'', September 28, 2007 page and 8.
*"AYF Get's Boost From State", ''Andover Townsman'', August 21, 2008, page 1 and 2.
*"AYF Get's Boost From State", ''Andover Townsman'', August 21, 2008, page 1 and 2.
*"Deadline on Youth Center", Andover Townsman, page 1 and 10.
*"Youth Foundation Gives Self-imposed Fundraising Deadline", ''Andover Townsman'', January 4, 2009, page B1 and B2.  
*"Youth Foundation Gives Self-imposed Fundraising Deadline", ''Andover Townsman'', January 4, 2009, page B1 and B2.  
*"Fresh Angle for Building Teen Center, ''Boston Globe Northwest'', January 20, 2008, page 1 and 6.
*"Fresh Angle for Building Teen Center, ''Boston Globe Northwest'', January 20, 2008, page 1 and 6.
*"Youths' sweet dream advances to finish lane," ''Andover Townsman'', April 25, 2013, p. 13.
*"Youths' sweet dream advances to finish lane," ''Andover Townsman'', April 25, 2013, p. 13.
*"Forging common ground," ''Andover Townsman'', May 16, 2013, p. 1.
*"Forging common ground," ''Andover Townsman'', May 16, 2013, p. 1.

Revision as of 13:40, 20 May 2015

Some news and articles on the proposed Andover Youth Center:

Andover teens began asking for a teen center in the 1960's. In 1994 when 3 Andover Teens committed suicide, the townspeople looked to building a teen center as a gathering place for Andover's youth. The town hired Bill Fahey to run a town-wide youth program and work towards construction of a center.

In July of 2000, the Andover Youth Foundation suggested land behind the Chandler Fire Station for a Youth Center.

Yvon and Noella Cormier of Andover donated $1.5 million to the Town of Andover for a youth center in West Andover. Under the agreement with the Andover Youth Foundation, the town will provide 6 acres in West Andover. The center would be called the Cormier Family Youth Center. Yvon owns the Cormier Construction Company.

Funding and other issues, such as playing field availability and the proximity of a landfill, plagued the project for the West Andover site. In December of 2005 $1 million dollar in infrastructure costs were added to the price tag delaying a June 2006 start date for construction of a Youth Center.

In 2006, a location downtown was discussed, but the article asking the Town for $900,000 was withdrawn from the Town Warrant. Selectman Brian Major suggested a Special Town Meeting in the fall to deal with the youth center.

The 2007 Town Meeting voted to use land behind Doherty Middle School. The suggestion was made at that time to build space that would be shared as a Youth Center and a Senior Center. Funding continued to be an issue. A private foundation - the Andover Youth Foundation was established to raise money and coordinate the process of building a youth center. A public project is required to pay state-set prevailing wages. Since a private organization is not the cost of the project is reduced substantially. Peg Campbell was promoted to the Foundation's president in June of 2007.

The Special Town Meeting in the Spring of 2013 approved using half of the $1.4 million Wood Trust (a fund established for the benefit of senior citizens) on the new Cormier Family Youth Center. The funding of the Cormier Family Youth Center came from a combination of town money and fundraising.



See

  • "Foundation: Give us Land, We'll Raise the Money," Andover Townsman, July 6, 2000.
  • "Youth Center Gets $30K From Andonna," Andover Townsman, September 27, 2001.
  • "Couple's Gift Boosts Project," Eagle Tribune, October 1, 2001.
  • "Youth Center $75,000 Richer," Andover Townsman, November 5, 2001.
  • "$120K raised at Telethon for Youth Center," Andover Townsman, February 12, 2004.
  • "Youth Center Price Tag Grows to $4.2 Million", Eagle Tribune, December 22, 2005.
  • "New Center Further off Schedule," Boston Globe, January 22, 2006.
  • "Fall Meeting Discussed for Youth Center Vote," Andover Townsman, April 6, 2006.
  • "New Youth Center Leader Wants Project Finished in 2 Years", Andover Townsman, June 14, 2007, page 1 and 2.
  • "Foundation: Pact Could Save $1M-plus", Andover Townsman, June 21, 2007
  • "State Ruling Could Save $1M on Youth Center", Eagle Tribune, July 18, 2007 page 1 and 3.
  • "Youth Center May Cost Extra $2M", Eagle Tribune, September 28, 2007 page and 8.
  • "AYF Get's Boost From State", Andover Townsman, August 21, 2008, page 1 and 2.
  • "Youth Foundation Gives Self-imposed Fundraising Deadline", Andover Townsman, January 4, 2009, page B1 and B2.
  • "Fresh Angle for Building Teen Center, Boston Globe Northwest, January 20, 2008, page 1 and 6.
  • "Youths' sweet dream advances to finish lane," Andover Townsman, April 25, 2013, p. 13.
  • "Forging common ground," Andover Townsman, May 16, 2013, p. 1.
...Youths' sweet dream advances to finish lane.... click to enlarge


  • "Youth Center scores key funding: Special Town Meeting vote takes project to $5.4M," Andover Townsman, May 9, 2013, p.1.
  • "Youth Center seeing final changes: expanded gym, generator proposed," Andover Townsman, June 20, 2013, p. 1.
  • "Youth Center expansion, upgrade approved: Two accounts tapped to supplement project," Andover Townsman, June 27, 2013, p. 1.
  • "Youth Center construction set for October," Andover Townsman, August 15, 2013, p. 1.
  • "Cormier Youth Center pact finally OK'd as bid deadline nears," September 12, 2013, p. 5.
  • "Roadblock for Youth Center: Bids cause snag in ground-breaking," Andover Townsman, October 10, 2013, p. 1.