2002 - In September Main Street Fire Station was razed and construction was begun on a new public safety center to house both fire and police. The police station was completed first. Mello Construction was the construction company for the Safety Center.
See
- Eagle Tribune, September 17, 2002
2003 - Construction on the Fire Station actually began in May 2003 and completed in July of 2004.
See
- "Town: Another Year for the Safety Center," Andover Townsman, May 8, 2003, page 1
2004 - The fire station was completed in July 2004
See
- "Public Safety Center: Complex Complete This Week," Andover Townsman, July 1, 2004, page 1