1829 - An engine house was built for the Friendly Fire Service, a private company.
See
1833 - Town Meeting voted the sum of $365 to build an engine house on Essex Street.
1862 - The Friendly Fire Society was renamed the Shawsheen Steam Fire Engine Company.
1895 - The Ballardvale Station was relocated to the corner of Andover Street and Clark Road.
See
- Andover a Century of Change:1896 - 1996 by Eleanor Motley Richardson, (974.45 Ric), page 194.
1924 - Andover established a Fire Department with Charles Emerson appointed as the first Fire Chief. By then "horses had become a thing of the past."
See
- "1924," Andover, What It Was, What It Is: 300th Anniversary, May 30 - June 2, 1946, (974.45 And)
1966 - A new fire station was built in West Andover on Chandler Road.
See
- Andover a Century of Change:1896 - 1996 by Eleanor Motley Richardson, (974.45 Ric), page 194.
2002 - In September Main Street Fire Station was razed and construction was begun on a new public safety center to house both fire and police. The police station was completed first. Construction on the Fire Station actually began in May 2003 and completed in July of 2004.
See
- Eagle Tribune, September 17, 2002
- "Town: Another Year for the Safety Center," Andover Townsman, May 8, 2003, page 1
- "Public Safety Center: Complex Complete This Week," Andover Townsman, July 1, 2004, page 1
2006 - There are three fire stations in Andover:
- Central Headquarters at 32 Main Street
- West Fire Substation at 200 Greenwood Road
- Ballardvale Fire Substation at 1 Clark Road